| Installation   Operation   Service Manual   for   Forced Draft Steam   Boilers   BRYAN BOILERS   783 N. CHILI AVENUE, PERU, INDIANA 46970   Telephone: 765-473-6651 / Fax: 765-473-3074   MINIMUM CLEARANCES   NOTE: These boilers are intended to be installed in a room which is large compared to the size of   the boiler. They are not intended for alcove installation and are suitable for installation on non-   combustible flooring only.   D-SERIES   F-SERIES1   CL-SERIES   K-SERIES   RV, RW & AB SERIES   DIMENSION   WATER/   STEAM   OVER   50#   WATER   STEAM   OVER   50#   WATER   STEAM   OVER   50#   WATER   STEAM   OVER   50#   WATER   /STEAM   TO 50#   STEAM   OVER   50#   STEAM   TO 50#   /STEAM   TO 50#   /STEAM   TO 50#   /STEAM   TO 50#   A B 18"   24"   18"   48"   24"   36"   24"   36"   96"   24"   18"   48"   18"   18"   18"   48"   96"   36"   36"   36"   24"   48"   24"   24"   24"   24"   36"   24"   24"   24"   18"   48"   24"   24"   24"   36"   24"   24"   24"   24"   24"   48"   24"   24"   32"   24"   48"   24"   24"   32"   CV & CH   D EL & ER   1 - F-Series boilers are approved for installation on combustible flooring. Do not install on carpeting.   A - Clearance above boiler   B - Front of boiler   CV - Clearance from gas vent, measured vertically above pipe   CH - Clearance from gas vent, measured horizontally or below pipe   D - From back of boiler   EL - Left side of boiler   ER - Right side of boiler   These clearances are general minimum clearances. Local codes may dictate larger clearances.   1.4 BOILER CONNECTIONS   1.4.1 GENERAL   tank. This valve can then be adjusted to   bypass excess pump capacity to better   control the boiler feed rate.   Do not run any pipes along the access panel   side of the boiler. Maintain clearances as   shown on the dimensional drawing for   servicing of the boiler tubes. Provide at least   36" from the gas train and burner, unless a   larger dimension is indicated on the   dimensional. All piping should be designed   and installed to avoid any loadings on the   boiler connections or piping.   1.4.4 SAFETY RELIEF VALVE(S)   A connection is provided in the top of the   boiler for the relief valve. The relief valve   discharge piping must be the same size as   the relief valve discharge opening. Avoid   over-tightening as this can distort valve seats.   All piping from relief valve must be   independently supported with no weight   carried by the valve.   1.4.2 STEAM SUPPLY CONNECTION   A steam shut-off valve must be installed   between each boiler and the steam main.   This valve must be of the outside screw and   yoke design to allow indication from a   distance whether the valve is open or closed.   1.4.4 BLOWDOWN CONNECTION   Blowdown valve(s) must be full size of the   connection on the boiler. Steam boilers 15   psig and below require at least one blowdown   valve. Higher pressure boilers require two   blowdown valves with one or both valves   being slow opening type. Each water column   and float type low water cut-off must be   equipped with a blowdown valve.   1.4.3 FEEDWATER CONNECTION   Install a check valve and a globe valve   between the feed pump and the boiler. It is   also recommended to install a globe valve   between the feed pump and the receiver   1.5 GAS SUPPLY CONNECTION - FORCED DRAFT UNITS   The installation must conform completely to the   requirements of the authority having jurisdiction,   or in the absence of such, requirements shall   conform in the U.S. to the current National Fuel   Gas Code, ANSI Z223.1-1984, or in Canada to   the current Installation Code for Gas Burning   Appliances and Equipment (CAN/CGA B149.1-   M91), or Oil Burning Equipment (CSA B139-   M91), and applicable regional regulations for the   class; which should be followed carefully in all   cases.   Drip leg must be installed on gas supply piping.   Consult the local gas utility company for   inspection and authorization of all gas supply   piping and flue connections.   The regulator vent line must be vented to outside   of building on any boiler equipment with electric   gas pilot ignition.   1.5.1 DRIP LEG   1.5.3 VENTING OF GAS TRAIN COMPONENTS   Gas pressure regulator - The regulator must be   vented to the outside air, using minimum 1/4"   tubing or pipe. The vent line should terminate in a   downward direction to be free of restriction.   A drip leg or sediment trap must be installed in   the gas supply line. See Fig. 1.5A. The gas line   must be connected to a supply main at least as   large as the gas train connection at the boiler.   This connection should be made with a union so   that the boiler gas train components and burner   may be easily removed, if necessary, for service.   Diaphragm gas valves (V48A or V88A) - The vent   line off of these gas valves must be vented to   outdoors, the same as the regulator.   1.5.2 GAS PIPING LEAK TEST   After completion of the gas piping hookup, the   installation must be checked for leaks, using a   soap and water solution. Disconnect the boiler   and gas train from the gas supply piping during   any pressure testing of the gas supply system.   Normally open vent valves - These valves must   be piped to outdoors using pipe no smaller than   that of the valve.   Gas pressure switches - Vent these switches to   outdoors using a minimum of 1/4" tubing or   piping.   FIGURE 1.5A: GAS BURNER CONNECTION   NOTE: USE PIPE COMPOUND, WHICH IS RESISTANT TO THE ACTION OF LIQUID PETROLEUM   GAS. DO NOT USE TEFLON TAPE.   1.6 ELECTRICAL CONNECTION   IMPORTANT: All electrical connections must   conform to the National Electrical Code and to all   other applicable State and Local Codes. Forced   details.   Equipment Grounding - The boiler must be   grounded in accordance with the American   National Standard Electrical Code, ANSI/NFPA   #70-1981.   draft boilers may require   a high voltage   connection. See boiler wiring diagram and   equipment list for   1.7 COMBUSTION AIR SUPPLY   IMPORTANT: Positive means for supplying an   ample amount of outside air, allowing complete   combustion of the gas, must be provided.   boiler is not equipped with a draft control device   (so no air is required for draft control).   COMBUSTION AIR OPENINGS   REQUIRED:   - AREA   Movable combustion air dampers, automatic or   manually adjustable, must be electrically   interlocked with the boiler to prevent boiler   operation if the dampers are closed.   Openings directly through outside wall -   One opening within 12 inches of the ceiling plus   one opening within 12 inches of the floor. Each   opening must have a minimum free area of 1   square inch per 4,000 Btu of total input of all air   using appliances in the room.   Combustion air openings must never be blocked   or obstructed in any manner.   The boiler room must be at a positive or neutral   pressure relative to the outdoors. A negative in   the boiler room will result in downdraft problems   and incomplete combustion due to lack of air.   Example: A boiler room having two boilers with   500,000 Btu input would require two openings   through an outside wall, and each opening must   have at least 250 square inches of free area.   Openings through vertical ducts -   One duct in the ceiling plus one duct terminating   within 12 inches of the floor. Each opening must   have a minimum free area of 1 square inch per   4,000 Btu of total input of all air-using appliances   in the room.   Example: A boiler room having four boilers with   250,000 Btu input would require two ducts, one in   the ceiling and one terminating near the floor,   each opening having at least 250 square inches   of free area.   WARNING!   Failure to provide an adequate air supply will   result in boiler damage and hazardous conditions   in the building (fire and asphyxiation hazard as   well as equipment damage).   COMBUSTION AIR: Complete combustion of   natural or propane gas requires approximately   ten cubic foot of air (at sea level and 70 F) for   each 1000 Btu of boiler input. In reality, additional   air is required to achieve complete combustion.   Air is also required for the proper operation of the   appliance draft diverter or barometric damper.   The combustion air opening recommendations   below are designed to provide the air needed for   atmospheric gas fired boilers which are equipped   with either draft diverters or barometric dampers.   Combustion air openings for boilers which are   equipped with forced draft burners may be   reduced to 70% of that required for atmospheric   gas fired boilers. This is because the forced draft   Openings through horizontal ducts -   One duct opening within 12 inches of the ceiling   plus one duct opening within 12 inches of the   floor. Each opening must have a minimum free   area of 1 square inch of per 2,000 Btu of total   input for all equipment in the room. NOTE: No   rectangular duct may have a dimension of less   than 4 inches.   Example: A boiler room having 1 million Btu total   input would require two ducts, one in the ceiling   and one near the floor, each opening must having   at least 500 square inches of free area.   Ventilation Air: In addition to air needed for   combustion, sufficient air must be supplied for   ventilation, including air required for comfort and   proper working conditions for personnel in the   boiler room. In colder climates, provision should   also be made to heat the boiler room, if   necessary, for personnel comfort.   disposal. The boiler room and the combustion air   supply must not be exposed to the fumes. Such   fumes include, but are not limited to, carbon   monoxide, hydrogen sulfide, ammonia, chlorine,   and halogenated hydrocarbons.   NOTE:   Halogenated   hydrocarbons   are   particularly injurious and corrosive after exposure   to high temperatures.   CAUTION   Protection from combustion air contamination:   Where corrosive or flammable process fumes are   present in the vicinity of the boiler room or the air   stream for the combustion air supply, it is   essential that suitable means be provided for their   safe   1.8 CHIMNEY, FLUE PIPE & DRAFT CONTROL - FORCED DRAFT BOILERS   CODE COMPLIANCE   ESTIMATING FLUE GAS FLOW RATE (ACFM)   Flue gas volumetric flow rate in SCFM (standard   cubic feet per minute) and ACFM (actual cubic   feet per minute) can be estimated by using the   information in 1.8.1A. Divide the Total Input of   appliances connected to the chimney or vent by   1000. Then multiply this result times the factor   listed in the SCFM and ACFM table. The ACFM   data is required for determining stack exit velocity   and induced draft fan requirements.   The installation must conform to the requirements   of NFPA 54, the National Gas Code (ANSI   Z223.1-1984), Part 7, "Venting of Equipment", or   to the applicable requirements of all local building   codes. For factory-built and listed chimney   systems (such as type B vent), consult the   system manufacturer's instructions for correct   installation procedures. Gas vents may be of any   of the construction types listed in this manual. No   portion of a venting system may extend into or   pass through any circulating air duct or plenum.   ESTIMATING STACK EXIT VELOCITY   First, determine the ACFM for the stack as   described above. Multiply the total ACFM times   the Velocity Factor from the Velocity Table in   Table 1.8.1B for the stack diameter used. The   result is the Stack Exit Velocity in feet per second.   MINIMUM SAFE PERFORMANCE   Venting systems must be designed to develop   positive flow adequate to remove flue gases to   the outside atmosphere. Guidelines are provided   in this manual and in the National Fuel Gas Code,   NFPA 54, for sizing and design of flue gas   venting systems. For additional reference to good   practice in vent design, refer to the "Chimney,   Gas Vent, and Fireplace Design" chapter of the   ASHRAE Equipment Handbook.   ESTIMATING STACK EMISSIONS   Table 1.8.1C lists approximate emissions of NOx   (oxides of nitrogen) and CO (carbon monoxide).   The table lists both the concentration, in parts per   million (ppm), and the flow rate, in pounds per   hour (PPH), of each compound: Divide the total   input of appliances connected to the chimney or   vent by 1,000,000. Then multiply this result times   the value listed in the table for PPH emissions.   OUTSIDE VENTS AND CHIMNEYS   Outside uninsulated single wall pipe is not   recommended for use in cold climates for venting   gas-fired   appliances   since   temperature   differentials may cause corrosion in such pipe, as   well as poor draft on start ups. When local   experience indicates that condensate may be a   problem, provisions should be made to drain off   the condensate in the gas vent or chimney.   MANUAL REFERENCES   See Figure 1.8.1 for a graphics listing of   applicable sections of this manual for each   section of the vent system.   FIG. 1.8.1: VENT DESIGN INSTRUCTION -   REFERENCES   TABLE 1.8.1A: ESTIMATING FLUE GAS VOLUMETRIC FLOW RATE   Approximate Flue Gas VOLUMETRIC FLOW RATE   (Per 1000 Btu/hr Input)   (Multiply factor listed times boiler input in MBH)   SCFM Per   1000 Btu/hr   INPUT   ACFM Per   1000 Btu/hr   INPUT   APPROXIMATE   FLUE GAS   BOILER TYPE   TEMPERATURE   Water & 15# Steam   Gas Fired   0.230   0.230   0.402   0.402   450 F   450 F   Oil Fired   150# Steam   Gas Fired   0.230   0.230   0.425   0.425   500 F   500 F   Oil Fired   TABLE 1.8.1B: STACK EXIT VELOCITY   Estimated STACK EXIT VELOCITY Calculation   (Multiply total ACFM times the velocity factor below velocity in feet per second)   STACK INSIDE   VELOCITY   FACTOR   STACK INSIDE   VELOCITY   FACTOR   STACK INSIDE   VELOCITY   FACTOR   DIAMETER (Inches)   DIAMETER (Inches)   DIAMETER (Inches)   6 7 0.0849   0.0624   0.0477   0.0306   0.0212   0.0156   0.0119   18   20   22   24   26   28   32   0.00943   0.00764   0.00631   0.00531   0.00390   0.00340   0.00298   34   36   38   40   48   60   0.00264   0.00236   0.00212   0.00191   0.00133   0.00085   8 10   12   14   16   TABLE 1.8.1C: ESTIMATING FLUE GAS EMISSIONS   Estimated Emissions (Volumetric Flow Rate Per Million Btu/hr Input)   (Multiply PPH listed times boiler input divided by 1,000,000)   BOILER   TYPE   PARTICULATES   NOx   CO   SOx   Hydrocarbons   PPH per   MMBH   PPM   PPH per   PPM   PPH per   MMBH   PPM   PPH per   PPM   PPH per   PPM   MMBH   MMBH   MMBH   Gas Fired   Oil Fired   N/A   N/A   20   0.049   50   70   0.194   0.018   200   18   N/A   N/A   290   0.010   10   4 0.020   0.068   0.286   0.004   1.8.2 CLEARANCES   The vent system and draft control devices must   be installed so as to achieve the clearances to   surfaces outlined in Table 1.2.1, Minimum   Clearances chart, in this manual. See also Table   1.8.9 for vent clearances. All clearances must   comply with the National Fuel Gas Code   (NFPA54), and with all   local and state building codes. The clearances   described in this manual are intended to be   general guidelines only, additional requirements   may occur because of local building design   regulations.   1.8.3 BOILER ROOM PRESSURIZATION   The boiler room must be supplied with adequate   air for combustion and for proper operation of   draft control devices (barometric dampers or draft   diverters) as outlined in "Combustion Air Supply",   Section 1.7 of this manual.   WARNING   THE BOILER ROOM MUST BE MAINTAINED   AT A POSITIVE OR NEUTRAL PRESSURE   (RELATIVE TO OUTDOORS) AT ALL TIMES.   EXHAUST FANS OR CONNECTIONS FROM   THE BOILER ROOM TO ZONES OF NEGATIVE   INDUCED DRAFT FAN WILL BE REQUIRED.   FURTHER, THE BOILER MUST BE PROVIDED   WITH A BAROMETRIC DRAFT CONTROL -   NOT WITH A DRAFT DIVERTER. THE FAN   MUST BE INTERLOCKED WITH THE BOILER   AND A DRAFT PROVING SWITCH MUST BE   INSTALLED TO PREVENT OPERATION OF   THE BOILER IF THE FAN SHOULD FAIL TO   OPERATE.   PRESSURE   (AIR   DUCTS,   NEGATIVE   PRESSURE ROOMS, ETC.) WILL CAUSE   NEGATIVE PRESSURE IN THE BOILER   ROOM. SUCH CONDITIONS WILL CAUSE   HAZARDOUS OPERATION OF THE BOILER   AND INTRODUCTION OF COMBUSTION   PRODUCTS INTO THE BUILDING AIR.   IT ALSO MAY BE ADVISABLE TO INSTALL AN   AUTOMATIC VENT DAMPER IN THE VENT   SYSTEM   TO   PREVENT   BACKFLOW   IF THE BOILER ROOM MUST BE UNDER A   NEGATIVE PRESSURE AT ANY TIME, AN   THROUGH THE VENT SYSTEM DURING   BOILER OFF CYCLES. SEE FOLLOWING   SECTION ON AUTOMATIC VENT DAMPERS.   1.8.7 ACCEPTABLE VENT TYPES   LISTED GAS VENTS   installed in accordance with nationally recognized   building codes or standards.   Listed gas vents must be applied only on those   applications for which they are listed. Type B gas   vents are NOT listed for use on forced draft   appliance vent systems.   MASONRY CHIMNEYS FOR RESIDENTIAL   APPLICATIONS MUST BE LINED WITH FIRE-   CLAY FLUE LINING (KX C315 OR THE   EQUIVALENT) WITH THICKNESS NOT LESS   THAN 5/16 INCH OR WITH A LINER OF OTHER   APPROVED MATERIAL THAT WILL RESIST   CORROSION, SOFTENING OR CRACKING   FROM FLUE GASES AT TEMPERATURES UP   TO 1800 F.   Installation of these vents must comply with the   vent listing, with the vent manufacturer's   instructions and with complete adherence to the   codes and clearances as outlined previously.   PRESSURIZED VENT SYSTEMS   Some Bryan Boilers (unless specifically fitted for   the application) are not suitable for operation on a   pressurized vent systems. Refer to Section 2 of   this manual for the allowable range of vent   pressure for each series. The RV, RW, and AB   series boilers are designed for pressurized vent   systems. All others require a neutral pressure.   EXISTING   CHIMNEYS   SHOULD   BE   INSPECTED FOR UNSAFE CONDITIONS,   SUCH AS DETERIORATED MASONRY AND   EXCESSIVE SOOT OR OTHER BLOCKAGE OR   POTENTIAL BLOCKAGE. SEE ALSO SECTION   1.8.6.   EXISTING CHIMNEYS MUST BE PROPERLY   SIZED FOR THE FLUE GAS LOADING TO BE   USED. THAT IS, IF AN EXISTING CHIMNEY IS   USED FOR A SMALLER TOTAL INPUT THAN   ITS ORIGINAL DESIGN, A LINER OR VENT IS   REQUIRED. THE USE OF A PROPERLY SIZED   GAS VENT OR LINER WILL PREVENT   DETERIORATION OF THE CHIMNEY DUE TO   THE EXCESSIVE CONDENSATION WHICH   RESULTS ON OVERSIZED SYSTEMS.   SINGLE-WALL METAL PIPE   Single-wall metal pipe must be of galvanized   sheet or other approved non-combustible   corrosion resistant material, with minimum   thickness per Table 1.8.7, from the National Fuel   Gas Code. Single-wall metal pipe should be   insulated to prevent excessive heat in the boiler   room and to avoid ignition and spillage problems   as well as corrosion from excessive   condensation.   MASONRY, METAL AND FACTORY BUILT   CHIMNEYS   WARNING   UNDER NO CIRCUMSTANCES SHOULD THE   FLUE PIPE BE CONNECTED TO THE   CHIMNEY OF AN OPEN FIREPLACE.   Installation of factory built vents and chimneys   must comply with the vent listing, with the vent   manufacturer's instructions and with adherence to   the codes and clearances as outlined herein.   Masonry or metal chimneys must be built and   TABLE 1.8.7A   TABLE 1.8.7B   WATER BOILER & STEAM BOILERS TO 50 PSIG   (STEAM BOILERS OVER 50 PSIG)   Diameter of   Connector, Inches   Minimum Thickness,   Inch (Gauge)   Diameter of   Connector, Inches   Minimum Thickness,   Inch (Gauge)   6 to 10   10 to 12   12 to 16   16 +   0.023 (24)   0.029 (22)   0.034 (20)   0.056 (16)   14 and less   14 to 16   16 to 18   18 +   0.053 (16)   0.067 (14)   0.093 (12)   0.123 (10)   1.8.5 VENT CONNECTORS (HORIZONTAL RUNS)   CONSTRUCTION   Supports should usually be overhead hangers, of   Vent connectors may be of any of the acceptable   constructions listed in this manual.   load bearing capacity appropriate for the weight   involved.   AVOID UNNECESSARY BENDS   LOCATION   The vent connector must be installed so as to   avoid turns or other construction features which   create excessive resistance to flow of flue gases.   When the vent connector used for an appliance   having a draft hood must be located in or pass   through a crawl space or other area difficult to   access or which may be cold, that portion of the   vent connector must be of listed double wall Type   B gas vent material, or of material having   equivalent insulation qualities. Single wall metal   pipe used as a vent connector must not pass   through any floor or ceiling.   JOINTS   Vent connectors must be firmly attached to draft   diverter outlets or boiler flue collars by sheet metal   screws or other approved means. Vent connectors   of Type B vent material must be assembled in   accordance with the vent manufacturer's   instructions. Joints between sections of connector   piping must be fastened using sheet metal screws   or other approved means.   CHIMNEY CONNECTION   In entering a passageway in a masonry or metal   chimney, the vent connector must be installed   above the extreme bottom to avoid stoppage.   Means must be employed which will prevent the   vent connector from protruding so far as to restrict   the space between its end and the opposite wall of   the chimney. A thimble or slip joint may be used to   facilitate removal of the vent connector. The vent   connector must be firmly attached to or inserted   into the thimble or slip joint to prevent the vent   connector from falling out.   SLOPE OR VENT CONNECTOR   The vent connector must be installed without any   dips or sags and must slope upward at least 1/4   inch per foot.   LENGTH OF VENT CONNECTOR   The vent connector must be as short as possible   and the boiler as close as practical to the chimney   or vent.   The horizontal run of an uninsulated vent   connector to a natural draft chimney or vent   servicing a single appliance must not be more than   75% of the height of the chimney or vent above   the vent connector.   The horizontal run of an insulated vent connector   to a natural draft chimney or vent servicing a single   appliance must not exceed 100% of the height of   the chimney or vent above the vent connector.   DAMPERS   Manually operated dampers must not be placed in   the vent connector. This does not exclude the use   of fixed baffles, locking quadrant dampers which   are welded in a fixed position, or automatic vent   dampers (when properly installed and interlocked   with the boiler gas controls).   USE OF THIMBLES   Vent connectors made of single wall metal pipe   must not pass through any combustible wall   unless they are guarded at the point of passage by   ventilated metal thimbles 6" larger in diameter than   the vent connector. This may be done only on   water boilers and steam boilers rated for operation   at no higher than 50 psig.   SUPPORT OF VENT CONNECTOR   The vent connector must be supported in   accordance with the vent manufacturer's   instructions and listing and with all applicable   codes. Support should also be independent of the   boiler or the draft diverter (when used). The vent   connector must be supported for the design and   weight of the material employed to maintain   clearances, prevent physical damage and   separation of joints, and to prevent sagging of the   vent connector.   SINGLE WALL METAL VENT PIPE USED TO   VENT STEAM BOILERS OPERATING OVER 50   PSIG MUST NOT PASS THROUGH WALLS OR   PARTITIONS   CONSTRUCTED   OF   COMBUSTIBLE MATERIAL.   1.8.6 CHIMNEY & VENT CONSTRUCTION (VERTICAL SECTION)   INSTALLATION   SYSTEMS   OF   FACTORY   BUILT   Alternatively, a non-ventilating thimble not less   than 18" above and 6" below the roof (with the   annular space open at the bottom and closed at   the top) may be used.   Listed gas vents and factory built chimneys must   be installed in accordance with their listings and   the manufacturer's instructions. Vents and   venting systems passing through roofs must   extend though the roof flashing, roof thimble or   roof jack.   INSPECTIONS OF CHIMNEYS   Before connection of a vent connector to a   chimney, the chimney passageway must be   examined to ascertain that it is clear and free of   obstructions. Cleanouts must be constructed   such that they will remain tightly closed when not   in use. Tee fittings used as cleanouts or   condensate drains must have tight fitting caps to   prevent entrance of air into the chimney at such   points. When an existing masonry chimney is   unlined and local experience indicates that vent   gas condensate may be a problem, an approved   liner or another vent must be installed. When   inspection reveals that an existing chimney is not   safe for the intended application, it must be rebuilt   to conform to nationally recognized standards,   relined with a suitable liner, or replaced with a gas   vent or chimney suitable for the appliances to be   attached.   INSTALLATION OF MASONRY OR METAL   CHIMNEYS   Masonry or metal chimneys must be built in   accordance with nationally recognized building   codes and standards.   INSTALLATION OF SINGLE WALL GAS VENTS   Single wall metal pipe may be used only for runs   directly from the space in which the appliance is   located through the roof or exterior wall to the   outer air. A pipe passing through a roof must   extend without interruption through the roof   flashing, roof jack or thimble. Single wall metal   pipe must not originate in any unoccupied attic or   concealed space. Additionally, it must not pass   through any attic, inside wall, concealed space or   through any floor. Minimum clearance must be   maintained between the single wall metal pipe   and any combustible surface as outlined in Table   1.8.9.   SUPPORT OF CHIMNEYS AND VENTS   All portions of chimneys must be adequately   supported for the design and weight of the   materials employed. Listed factory built chimneys   must be supported and spaced in accordance   with their listings and the chimney or gas vent   manufacturer's recommendations.   When a single wall metal pipe passes through an   exterior wall constructed of combustible material,   it must be guarded at the point of passage by a   ventilated thimble as described under "Use of   Thimbles" in Section 1.8.8 of this manual.   THE GAS VENT OR CHIMNEY MUST BE   SUPPORTED INDEPENDENTLY OF THE   BOILER TOP OR DRAFT DIVERTER.   MINIMUM REQUIRED DISTANCE FROM COMBUSTIBLE MATERIAL   EQUIPMENT TYPE   Listed Vent   not permitted   not permitted   Single Wall Metal Pipe   Factory Built Chimney   as listed   Water and 15 psig Steam Boilers   All Steam Boilers over 15 psig   18"   36"   as listed   1.8.7 MARKING OF GAS VENTS   In those localities where solid and liquid fuels are   used extensively, gas vents must be plainly and   permanently identified by a label reading:   "This gas vent is for appliances which   burn gas only. Do not connect to   incinerators or solid or liquid fuel burning   appliances."   The authority having jurisdiction must determine   whether their area constitutes such a locality.   This label must be attached to the wall or ceiling   at a point near where the gas vent connector   enters the wall, ceiling or chimney.   1.8.8 VENTING MULTIPLE APPLIANCES ON A COMMON VENT   COMMON GAS VENT   PRESSURIZED   CONNECTORS   DO NOT CONNECT THE FLUE OF AN   APPLIANCE VENTED BY NATURAL DRAFT TO   A VENT SYSTEM WHICH OPERATES UNDER   A POSITIVE PRESSURE.   VENTS   OR   VENT   When two or more openings (for vent connectors)   are provided in a chimney or gas vent, the   opening should be at different levels. They should   never be opposite one another.   When two vent connectors enter the same gas   vent or chimney, the smallest of the two should   enter at the highest position possible.   SOLID FUEL APPLIANCE VENTS   Gas appliances must not be vented to a vent or a   chimney which serves a solid fuel burning   appliance.   1.8.9 VENT AND CHIMNEY TERMINATIONS   HEIGHT ABOVE ROOF OR OBSTACLE   WATER BOILERS AND LOW PRESSURE   STEAM BOILERS: No less than 3 feet above the   roof and no less than 2 feet above any parapet or   obstacle closer than 10 feet from the vent outlet.   CLEARANCE FROM PUBLIC WALKWAYS   The vent exit of a mechanical draft system must   be at least 7 feet above grade when located next   to public walkways.   HIGH PRESSURE (OVER 15 PSIG) STEAM   BOILERS: No less than 10 feet higher than any   portion of any building within a distance of 25 feet   from the vent.   PROTECTION OF BUILDING MATERIALS   FROM   POSSIBLE   CORROSION   OR   DISCOLORATION FROM FLUE PRODUCTS   The products of combustion from gas or oil   contain potentially corrosive gases and high   temperatures. For this reason, the chimney or   vent exit must be designed to prevent exposure   of the building materials to the flue products.   Failure to do so may result in deterioration or   discoloration of building materials.   MINIMUM HEIGHT ABOVE DRAFT CONTROL   Chimneys and gas vents must extend at least 5   feet above the highest connected barometric draft   control or any appliance flue outlet.   CLEARANCE FROM AIR INLETS   The vent or chimney must terminate no less than   3 feet above any forced air inlet within a distance   of 10 feet. It must terminate no less than 1 foot   above, or 4 feet below, or 4 feet horizontally from,   any door, window or gravity air inlet into a   building.   VENT SUPPORT   The gas vent or chimney must be securely   positioned and supported. Guy wires or other   reliable means must be used to prevent   movement of the vent.   PROTECTION AGAINST BLOCKAGE OR   OBSTRUCTION   The chimney or vent exit design must prevent any   possibility of blockage by snow or any other   obstruction.   Listed gas vents must be terminated with a listed   cap, approved for use with the particular gas   vent.   Listed vent caps or roof assemblies must have a   rated venting capacity no less than the vent.   VENTILATING   SYSTEMS   HOODS   AND   EXHAUST   Single wall vents must terminate in an approved   cap which does not obstruct the exit. The   preferred type of cap for natural draft vented   atmospheric boilers is the Briedert Cap. This is   because of the protection this cap provides   against wind-generated downdrafts.   Ventilating hoods or exhaust systems may be   used to vent atmospheric gas appliances. When   these are used, however, such mechanical   exhaust devices must be electrically interlocked   with all appliances on the vent system. The circuit   must prevent the operation of any appliance on   the system if the hood or exhaust system is not in   operation.   Where there is no concern of high winds or   turbulence at the vent exit, a low resistance   conical cap may be used. See Fig. 1.8.12B for   typical dimensions. The diameter of this type cap   should be twice the vent diameter. The cap must   be securely positioned on the vent such as to   provide a clearance of one vent diameter above   the vent exit.   STACK CAPS   EVERY GAS VENT MUST BE SUPPLIED WITH   AN APPROVED VENT CAP WHICH WILL   PREVENT THE ENTRANCE OF RAIN OR   OTHER PRECIPITATION INTO THE VENT.   FAILURE TO PROVIDE SUCH A CAP MAY   CAUSE SEVERE BOILER CORROSION,   COMBUSTION PROBLEMS, OR BOTH.   FIG. 1.8.12B: LOW RESISTANCE VENT CAP   1.8.10 AUTOMATIC VENT DAMPERS   ONE APPLIANCE ONLY   INSTALLATION   An automatic vent must be installed such that it   serves only one appliance vent - that to which it is   properly interlocked.   The damper installation must comply with   Appendix I, J, or K of the National Fuel Gas   Code, NFPA 54. The installation must also   comply with the automatic vent damper listing,   the damper manufacturer's instructions and all   applicable local or state building codes.   LISTING REQUIREMENTS   Automatic vent dampers, if used, must be of a   listed type.   AUTOMATIC VENT DAMPERS MUST BE   INSTALLED ONLY BY QUALIFIED SERVICE   TECHNICIANS. FAILURE TO PROPERLY   INSTALL A VENT DAMPER WILL CREATE A   SEVERE HAZARD.   PERFORMANCE TEST   The automatic vent damper must be tested after   installation to assure its proper and safe   operation.   AUTOMATIC VENT DAMPERS MUST BE IN   THE OPEN POSITION AT ANY TIME THE   APPLIANCE MAIN GAS VALVE IS ENERGIZED.   1.8.14 SIZING OF CHIMNEY AND VENT   IMPORTANT   the gas input. Consult the factory or the local   Bryan Representative for the proper parts. For   the purpose of vent system sizing, assume full   input and determine sizing as if at sea level. The   derate factor of 4% per 1000 feet above sea   level accounts for the increased volume per   Btu/hr of flue products at high altitude.   The flue system calculations which follow in   Section 1.8.15 are applicable to double-wall or   insulated single wall breechings (vent connectors)   and stacks (vents). Do not apply these   calculations to uninsulated vent systems.   HIGH ALTITUDES   At altitudes of 2000 feet and higher, atmospheric   boilers must be derated. The amount of derate   required by the National Fuel Gas Code is 4% per   1000 feet above sea level. Boilers which are   shipped from the factory prepared for these   altitudes have the gas orifices properly sized for   this derate. The altitude and gas Btu content for   which the boilers have been constructed is listed   on the Equipment List/Submittal Data in the boiler   manual. The boilers will also be provided with a   label indicating that they have been prepared for   high altitude. If a boiler is to be installed at an   altitude other than that for which it was factory   built, orifices must be replaced to properly adjust   INDUCED DRAFT FANS   Occasionally, the characteristics of an installation   are such that a natural draft vent system will not   suffice. In such cases, induced draft may be   used. The vent system is then sized with an   available "pumping" action equal to the total   theoretical draft plus the static pressure capability   of the induced draft fan. This will result in a   smaller diameter vent than for a natural draft   system. Sizing of induced draft fans should be   done using the recommendations of the fan   manufacturer and the ASHRAE Handbook.   FIG. 1.8.14: SUGGESTED APPLIANCE VENTING PROCEDURE   MULTIPLE APPLIANCE INSTALLATIONS   individual venting is not possible, boilers may be   vented to a common breeching (vent connector).   See Fig. 1.8.14B for recommended design of   such a system. Note that connections of   individual boiler or appliance vents into the   common breeching should   Bryan recommends that boilers and other gas   appliances be individually vented when possible.   See figure 1.8.14A. Individual venting provides   better draft control and fuel efficiency, and is less   likely to cause condensation in the system. When   be done with 45   elbows and not by   provide a relatively constant flue gas velocity   through the vent system. Using a constant   diameter breeching will often result in poor draft   at the outermost appliances.   "bullheading" directly into the vent connector at   90 angles. "Bullhead" connections generally   cause excessive turbulence and poor draft   conditions. On vent connectors serving multiple   appliances, the diameter of the piping should be   increased at each appliance's entrance so as to   1.8.12 QUICK SELECTION FOR VENT SIZING CHARTS   GENERAL   must be checked against such local   These charts were generated using the   procedure described in Chapter 26 of the   ASHRAE Equipment Handbook (1979). The   results are consistent with those of the National   Fuel Gas Code.   requirements.   RECTANGULAR VENTS   Vent systems may be rectangular as well as   circular. Table 1.8.15F has been provided to give   the circular equivalent of rectangular duct. These   equivalent values account for the higher pressure   drop per cross section area for rectangular ducts.   The sizing herein is applicable to vent systems   utilizing double wall listed Type B vent as well as   single wall insulated vent with insulation   equivalent to double wall insulating value.   STEP 1: EQUIVALENT INPUT   CONTROL FACTOR   - DRAFT   Determine the boiler (system) Draft Control   This sizing procedure is not applicable to vent   systems utilizing single wall uninsulated vents or   vent connectors.   Factor, F1, from Table 1.8.15A.   Determine the boiler (or total system) input in   MBH. This is done by dividing the boiler (or total   system) input in Btu/hr by 1000.   The sizing information given herein is intended as   a general recommendation only. Vent sizing and   installation must comply with local codes.   Multiply the total input times factor F1.   The responsibility for assurance of such   compliance is that of the system designer and/or   the system installer. All sizing and installation   The equivalent input, I, (without altitude   correction) is then:   I = MBH x F1   eq. 15A   TABLE 1.8.15A: DRAFT CONTROL FACTOR F1   Multiply factor time input in MBH   Boiler Type   Factor, F1   1.000   Atmospheric with Draft Hood   Atmospheric with Barometric   Forced Draft Gas or Oil   0.741   0.602   STEP 2: EQUIVALENT INPUT - ALTITUDE   FACTOR   Determine the boiler (system) Altitude Correction   Factor, F2, from Table 1.8.15B.   The altitude correction factor, F2 for atmospheric   boilers is equal to 1, because their inputs are   already derated for altitude.   The equivalent input, I, with corrections for   altitude is:   Multiply the boiler (or total system) input times   factors, F2 and F1 for the equivalent input.   I = MBH x F1 x F2   eq. 15B   Table 1.8.15B ALTITUDE CORRECTION FACTOR, F2   (Multiple factor times sea level input, MBH)   Altitude (ft)   Factor, F2   Altitude (ft)   Factor, F2   0 to 1999   2000   2500   3000   3500   4000   4500   5000   5500   1.00   1.075   1.096   1.116   1.136   1.157   1.180   1.202   1.25   6000   6500   7000   7500   8000   8500   9000   10000   1.247   1.272   1.296   1.322   1.346   1.373   1.399   1.453   STEP 3: SELECT TRIAL DIAMETER   STEP 4: CALCULATE SYSTEM K-FACTOR   The system "k-factor" accounts for the pressure   drop through fittings and vent piping. It is   calculated by adding up the individual k-factors   for each of the fittings plus the k-factor for the   vent pipe(s).   Determine the NET STACK HEIGHT for the vent.   (The net stack height is the vertical distance from   the top of the atmospheric boiler draft control to   the top of the stack. On forced draft boilers it is   the distance from the boiler flue connection to the   top of the stack.)   From Table 1.8.15D find the k-factors for each of   the elbows, tee fittings, draft regulators, etc. in the   system. Then calculate the vent piping k-factor   from the formula:   Find the vent of TRIAL STACK DIAMETER. Enter   Table 1.8.15C at the Net Stack Height column   equal to the system net stack height. Then   proceed down the column to the input which is   just larger than the equivalent to an input which is   just larger than the Equivalent Input of the   system. Read the Trial Stack Diameter in the left   hand column.   kpiping = 0.4 x L/D   eq. 15C   L = total length of piping in feet   D = diameter of piping in inches   Add all the k-factors together to determine the   total system k-factor:   ktotal = kpiping + kfittings   eq. 15D   NOTE: This is only a trial diameter. Proceed to   Step 4 to calculate the system k-factor to   determine the actual stack diameter required.   NOTE: On multiple appliance systems, multiply   the k-factor times 1.5. This is required only on   atmospheric boiler vent systems, not on forced   draft systems.   Table 1.8.15D: Vent Fitting k-Factors   Vertical Draft Hood   Barometric Draft Control   1.50   0.50   Low Resistance Cap   Round Elbow, 90 deg F   Round Elbow, 45 deg F   0.75   0.30   Converging Exit   Cone   (D1/D2)4 - 1   (D1 is larger than D2)   Tee or 90 degF Breeching   Y Breeching   1.25   0.75   Tapered Reducer   1 - (D2/D1)4   (D1 is larger than D2)   STEP 5: CORRECT EQUIVALENT INPUT FOR   SYSTEM K-FACTOR   Multiply the equivalent input calculated in Step 2   times factor F3 from Table 1.8.15E. This step will   yield a new equivalent input, I:   The capacities listed in Table 1.8.15C are based   on a system k-factor equal to 7.5. For any other   k-factor, the vent capacity must be adjusted. This   is accomplished by adjusting the equivalent input   for the system using a k-factor correction factor,   designated F3.   I = MBH x F1 x F2 x F3 eq. 15E   Using this adjusted equivalent input, check the   stack diameter by following Steps 2 thru 3 again.   If the stack diameter remains the same, the sizing   is complete. If not, redo Steps 4 thru 5 etc. until   Refer to Table 1.8.15E for the equivalent input   correction factor which applies to the k-factor   calculated in Step 4. This factor is designated as   F3.   an   acceptable   result   is   achieved.   Table 1.8.15E: K-Factor Equivalent Input Correction Factor F3   K- Factor F3 K- Factor F3 K- Factor F3   K- Factor F3   K- Factor F3   1.00 0.37   1.50 0.45   2.00 0.52   2.50 0.58   3.00 0.63   3.50 0.68   4.00 0.73   4.50 0.77   5.00 0.82   5.50   6.00   6.50   7.00   7.50   8.00   8.50   9.00   9.50   0.86   0.89   0.93   0.97   1.00   1.03   1.06   1.10   1.13   10.00   10.50   11.00   11.50   12.00   12.50   13.00   13.50   14.00   1.15   1.18   1.21   1.24   1.26   1.29   1.32   1.34   1.37   14.50   15.00   15.50   16.00   16.50   17.0   17.50   18.00   18.50   1.39   1.41   1.44   1.46   1.48   1.51   1.53   1.55   1.57   19.00   19.50   20.00   20.50   21.00   21.50   22.00   22.50   23.00   1.59   1.61   1.63   1.65   1.67   1.69   1.71   1.73   1.75   Stack   Diam.   (in.)   Table 1.8.15C: Approximate Stack Capacities (MBH)   (Based on Atmospheric Boiler with Draft Hood)   5 7 10   12   150   15   20   25   30   35   40   280   45   50   320   60   70   80   90   100   450   125   510   150   550   200   640   6 100   120   140   170   200   220   250   270   300   350   380   400   430   7 130   160   190   210   240   270   310   340   360   390   410   430   480   510   550   580   620   690   760   870   8 180   210   250   280   310   360   400   440   480   510   540   570   620   670   720   760   810   900   990   1140   1450   1790   2580   3510   4590   5810   7170   8680   10330   12120   14060   16140   18360   20730   23240   41320   52290   64560   92970   9 220   270   320   350   390   450   510   560   600   640   680   720   790   850   910   970   1020   1260   1820   2480   3240   4100   5070   6130   7300   8570   9940   11410   12980   14650   16430   29210   36970   45650   65740   1140   1410   2040   2770   3620   4590   5670   6860   8160   9580   11110   12760   14510   16390   18370   32660   41340   51040   73500   1250   1550   2330   3040   3970   5030   6210   7510   8940   10490   12170   13970   15900   17950   20120   35780   45290   55910   80510   10   12   14   16   18   20   22   24   26   28   30   32   34   36   48   54   60   72   280   330   400   430   490   560   630   690   750   800   850   890   980   1060   1520   2070   2710   3430   4240   5130   6110   7170   8310   9540   10860   12260   13750   24400   30930   38190   55000   1130   1630   2220   2900   3670   4530   5480   6530   7660   8890   10200   11610   13110   14700   26130   33070   40830   58800   1200   1730   2350   3070   3890   4810   5820   6920   8130   9430   10820   12310   13900   15590   27710   35080   43310   62360   400   480   570   630   700   810   910   1000   1360   1770   2250   2770   3360   4000   4690   5440   6250   7110   8020   9000   1080   1470   1920   2430   3000   3630   4320   5070   5880   6750   7680   8670   9720   1150   1570   2050   2590   3200   3880   4610   5420   6280   7210   8210   9270   10390   1220   1660   2170   2750   3400   4110   4900   5750   6660   7650   8710   9830   1290   1750   2290   2900   3580   4340   5160   6060   7030   8070   9180   10360   1410   1920   2510   3180   3920   4750   5650   6640   7700   8840   10050   11350   12730   22630   28640   35360   50920   550   650   780   860   960   1110   1450   1830   2260   2740   3260   3830   4440   5100   5800   6550   7350   1240   1620   2050   2530   3060   3650   4280   4970   5700   6490   7320   8210   720   850   1020   1290   1600   1940   2300   2710   3140   3600   4100   4630   5190   9230   1120   1420   1750   2120   2530   2960   3440   3950   4490   5070   5670   10120   1250   1590   1960   2370   2820   3320   3850   4420   5020   5670   6360   910   1080   1340   1620   1930   2260   2630   3010   3430   3870   4340   7730   1130   1370   1630   1910   2220   2550   2900   3270   3670   6530   8260   10200   14700   11020 11620   19600 20660   24800 26140   30620 32280   44100 46480   11310 13060 14600 16000 17280 18470   14320 16530 18480 20250 21870 23380   17680 20410 22820 25000 27000 28870   25460 29400 32870 36000 38890 41570   9780 11690 12810   12070 14430 15810   17390 20780 22770   NOTE: The above vent input capacities in MBH (thousands of Btu/hr) are sea level ratings for double wall or insulated vents allowing for a system K factor of   7.5. Apply the correction factors for altitude, other k-factors and boiler draft control correction factors.   Table 1.8.15F: CIRCULAR EQUIVALENTS OF RECTANGULAR BREECHINGS & STACKS   WIDTH   HEIGHT (INCHES)   (INCHES)   6 7 8 8 9 8 8 9 10 12 14 16   10 10   10 11 11 12   18   11   13   15   16   17   19   20   21   22   23   24   24   25   27   29   31   33   34   20   11   13   15   17   18   20   21   22   23   24   25   26   27   29   31   33   35   37   22   12   14   16   18   19   20   23   24   25   26   27   28   31   33   35   37   39   39   24   12   15   17   18   20   21   23   24   25   26   27   28   29   32   34   37   39   40   26   13   15   17   19   21   22   24   25   26   27   28   29   31   33   36   38   40   42   28   13   16   18   20   21   23   24   26   27   28   29   31   32   35   37   40   42   44   30   14   16   18   20   22   24   25   27   28   29   31   32   33   36   39   41   44   46   36   15   15   17   20   22   24   26   27   29   31   32   35   36   39   42   45   48   50   42   16   19   21   23   26   28   29   31   33   34   36   37   39   42   46   49   52   55   48   17   20   22   25   27   29   31   33   35   37   38   40   41   45   49   52   56   59   54   17   21   23   26   29   31   33   35   37   39   40   42   44   48   52   56   59   62   60   18   21   24   27   30   32   34   37   39   40   42   44   46   50   55   59   62   66   6 8 9 8 10   12   14   16   18   20   22   24   26   28   30   36   42   48   54   60   10 11 12 13 14   11 12 13 14 15   10 11 13 14 15 16   10 12 14 15 16 17   11 13 15 16 17 19   11 13 15 17 18 20   12 14 16 18 19 20   12 15 17 18 20 21   13 15 17 19 21 22   13 16 18 20 21 23   14 16 18 20 22 24   15 17 20 22 24 26   16 19 21 23 26 28   17 20 22 25 27 29   17 21 23 26 29 31   18 21 24 27 30 32   1.8.16 SPECIAL APPLICATIONS   FLUE GAS ECONOMIZERS   HIGH EFFICIENCY APPLIANCES   When applying flue gas economizers, care must   be taken to assure that:   1. Proper draft must be maintained. This requires   that the gas side pressure drop be considered   and that the economizer exchanger must be   designed so as to allow cleaning.   2. The vent system materials must be considered,   regarding resistance from corrosion, which might   result from the lower flue gas temperature.   3. In general, it is recommended that the boiler   manufacturer be consulted when a flue gas   economizer is to be added.   High efficiency appliances require special   consideration in vent design because of the   reduced stack gas temperatures. Under no   circumstances can a condensing type appliance   be vented into the same vent system with other   appliances. The vent system for such appliances   must be provided by or specified specifically by   the manufacturer of the condensing appliance.   High efficiency non-condensing appliances   should   generally be installed only on vent   systems that are resistant to corrosion from flue   gas condensate. This generally requires stainless   steel vent construction.   1.9 BURNERS AND GAS TRAIN - FORCED DRAFT BOILERS   GENERAL   Oil supply lines must be sized for the circulation   Refer to separate manual on the forced draft   burner for start-up and adjustment procedures.   Do not attempt to start burner when excess oil   has accumulated, or when the combustion   chamber is full of gas, or if chamber is very hot.   rate of the burner pump. This is referred to as the   suction gear capacity of the pump. If a transfer   pump is used, it must have a pumping capacity   no less than the total suction gear capacity of all   burner pumps on the system. Refer to Burner   Manual for the suction gear capacity of standard   oil pumps. Two-pipe oil systems are   recommended in all cases, although a one-pipe   system might be acceptable on smaller boilers   (under 6 gph). Two-pipe systems tend to have   fewer problems with air entrainment in the oil. Air   in the oil will cause nuisance problems and   delayed ignition.   FUEL CONNECTIONS   Gas supply connections must comply with the   National Fuel Gas Code (NFPA54). Oil supply   connections must comply with NFPA31. Any   additional local or state codes must also be   adhered to.   1.10 PROCEDURES TO BE FOLLOWED BEFORE PLACING BOILER IN   OPERATION   1.10.1 HYDROSTATIC TEST OF BOILERS AND   SYSTEM   although the boiler is hydrostatically tested at the   factory, minor leaks in fittings and at attachments   can develop from shipping vibration or from   installation procedures. It is often necessary to   retighten such fittings after the installation and   after the boiler has been operated for some time.   Replace tube access panels before proceeding to   start boiler.   After completing the boiler and burner installation,   the boiler connections, fittings, attachments and   adjacent piping must be inspected for leaks by   filling the unit with water. The pressure should be   gradually increased to a pressure just below the   setting of boiler safety relief valve(s).   Remove the boiler tube access panels (see   dimensional drawing in this manual). Inspect the   tube to header joints to be certain that all tube   fittings are sealed. This is necessary because,   1.10.2 TEST OF GAS PIPING   Reference gas system test under Section 1.5,   "Gas Connection", in this manual.   START-UP AND OPERATION   STEAM BOILERS   WARNING:   IMPROPER SERVICING AND START-UP OF THIS EQUIPMENT MAY CREATE A   POTENTIAL HAZARD TO EQUIPMENT AND TO OPERATORS OR PERSONS IN THE   BUILDING.   SERVICING AND START-UP MUST BE DONE ONLY BY FULLY TRAINED AND   QUALIFIED PERSONNEL.   CAUTION:   BEFORE DISCONNECTING OR OPENING ANY FUEL LINE, OR BEFORE CLEANING OR REPLACING   PARTS OF ANY KIND, TAKE THE FOLLOWING PRECAUTIONS:   Turn OFF the main fuel shutoff valves, including the pilot gas cock if applicable. If the burner is a multiple   fuel type, shut OFF all fuel supplies.   Turn OFF all electrical disconnects to the burner, boiler and any other equipment or systems electrically   interlocked with the burner or boiler.   All cover plates, enclosures, and guards must be in place at all times except during maintenance and   servicing.   2.1 FIRING RATE ADJUSTMENT - ATMOSPHERIC GAS UNITS   2.1.1 The following procedures must be followed   carefully before putting the boiler in operation.   Failure to do so will present severe hazards to   equipment, operating personnel and building   occupants.   which firing rate system is used, see the boiler   Equipment List and Wiring Diagram.   2.1.4 ADJUST BOILER MINIMUM INPUT   After setting the correct Maximum input as   described in the Lighting Instructions, proceed to   adjust the minimum input as outlined below. This   applies only to those boilers which are designed   and equipped for two-stage (High/Low/Off) firing   or Modulation. On those boilers which are   equipped for ON/OFF firing only, no minimum   input adjustment is required. NOTE: the low firing   rate input is adjustable only on boilers equipped   with two-stage or modulating motorized gas   valves (V4055, V9055, or AH4 actuators) or with   motor-operated modulating butterfly gas valves.   The other two-stage firing systems (VR850 or   VR852 combination valves or dual diaphragm   valve type bypass systems) have a non-   adjustable minimum input rate.   2.1.2 ADJUST PILOT BURNER   Carefully follow the Lighting Instructions in the   boiler manual for the proper adjustment of the   pilot burner. This is absolutely essential before   attempting to adjust the main burner.   2.1.3 ADJUST BOILER INPUT(S)   The boiler input must be adjusted for both   maximum and minimum input values which are   listed on the boiler nameplate. First adjust the   maximum input rating using the method   described in Lighting Instructions in the Boiler   Manual. Refer to the following information for the   adjustment of the minimum input. To determine   the adjustment   NOTE   2.1.6 MINIMUM INPUT ADJUSTMENT - DUAL   DIAPHRAGM GAS VALVE HIGH/LOW BY-PASS   SYSTEM   THE LOW FIRE ADJUSTMENT SHOULD   RESULT IN A GAS PRESSURE ON THE   BURNER MANIFOLD EQUAL TO 1" WATER   COLUMN FOR NATURAL GAS AND 3" FOR   PROPANE GAS.   The minimum input on this control system is NOT   adjustable. The maximum input must be properly   set as outlined in Lighting Instructions. This   system consists of two V48A (120 volt coil) or two   V88A (24 volts coil) diaphragm gas valves which   are piped in parallel. The minimum input is   controlled by an orifice plug installed in a coupling   in the by-pass piping (low fire valve piping), sized   for approximately 1" w.c. manifold pressure at low   fire natural gas (2" w.c. if propane gas). When the   high fire gas valve is not activated, gas flows only   through the bypass piping. When the high fire gas   valve is activated, gas will flow though both   valves achieving full input.   2.1.5 MINIMUM INPUT ADJUSTMENT   COMBINATION GAS VALVES (VR850 OR   VR852)   The minimum input on these gas valves is NOT   adjustable. The maximum input must be properly   set as outlined in Lighting Instructions. See the   manufacturer's instructions on the VR850 or   VR852 included in the Boiler Manual for further   information.   - 2.2 FIRING RATE ADJUSTMENT - GAS METER READINGS   2.2.1 CHECKING BURNER INPUT   calculated from this timing. The method is   The burner input rate can be checked by taking   readings from the gas meter. Please note   checking the rate with a meter is the only way to   be sure of input. Manifold readings are only an   approximate value and may vary from unit to unit.   described in Lighting Instructions. If the meter is   not calibrated for gas temperature and pressure,   correction factors must be applied to determine   correct rate in SCFH (standard cubic feet per   hour). Consult the National Fuel Gas Code (ANSI   Z223.1, NFPA 54) or the local gas utility for   further information. Refer to Table 2.2A for   correction factors for the gas pressure at the   meter. Refer to Table 2.2B for the gas   temperature correction factors.   In order to obtain accurate data, there must be no   other appliances using gas from the same meter   while the burner input rate is being checked. The   test hand on the meter should be timed for   several revolutions. The input rate in cubic feet   per hour is   Table 2.2A - Pressure Correction   Table 2.2B - Temperature Correction   Gas Pressure at Meter   7" w.c.   Correction Factor   Gas Temp. at Meter   Correction Factor   0.920   1.017   1.034   1.051   1.061   1.136   1.340   40   50   60   70   80   90   F F F F F F 14" w.c.   0.902   21" w.c.   0.885   1 psig   0.868   2 psig   0.852   5 psig   0.836   2.3 SAFETY SHUT-OFF DEVICES (FLAME SUPERVISION)   2.3.1 FLAME SUPERVISORY SYSTEM   flame loss. In addition to the information given in   The boiler is equipped with a flame supervisory   system, either the Thermocouple type (such as a   combination gas valve or a pilotstat) or electronic   type (such as the RA890, or RM7895). The   purpose of this device is to detect the main or   pilot flame, depending on the type of device, and   control the gas valves accordingly. The device   must be checked for proper operation. See   Lighting Instructions in the Boiler Manual for the   correct procedure. The flame supervisory system   must be tested to assure that it will shut off the   main gas valves in case of a   Lighting Instructions, operating sequence and   troubleshooting information may be found in the   manufacturer's instructions in the Boiler Manual.   2.3.2 AUTOMATIC (ELECTRIC) IGNITION   SYSTEMS   On boilers equipped with automatic electrically   ignited pilots, follow the procedures described in   Lighting Instructions and test the controls for   proper operation.   2.4 LIMIT CIRCUIT CUT-OUT TEST   2.4.1 PROTECTIVE DEVICES   All operating and limit controls and low water   cutoffs must be tested for proper operation.   water feeder combination) or electric probe type   auxiliary control. These water level controls are   intended to sense (and control) the level of the   water in the boiler. They operate to shut off the   boiler if the water level drops below their sensing   level. The low water cut-off and water level   controls must be operationally tested by manually   lowering the boiler water level (by opening the   boiler blowdown valve for probe controls, and by   opening the control blowdown valve for float type   controls). The boiler should cycle off when the   water level drops below the control point of the   low water cut-off. When the water level is   restored, the boiler should cycle back on.   Depress the manual reset button of devices   which require manual reset in order to restore the   boiler to operation. Carefully read the enclosed   literature on the low water cut-off controls,   particularly installaing, operating and servicing.   2.4.2   STEAM   PRESSURE   OPERATING   CONTROL   The steam pressure in the boiler is regulated by   the Boiler Operator. This is a pressure control   which senses the steam pressure and turns the   boiler on and off accordingly. This control must be   operationally tested. Adjust the pressure setting   on the control to a pressure less than the boiler   pressure (as shown on the boiler pressure   gauge). The control should turn the boiler off.   Restore the control setting to normal. The boiler   should cycle on.   2.4.3 HIGH LIMIT CONTROL   At least one additional pressure control is   provided as the high limit control. It is set at a   pressure above the operator to act as a back-up   should the operator fail. The high limit control   must be operationally tested. With the boiler   operating, decrease the pressure setting of the   limit control below the current pressure of the   boiler. The boiler should cycle off. Restore the   high limit control setting to normal (pushing rest   button if it is a manual reset type). The boiler   should now cycle on.   2.4.5 COMBINATION LOW WATER CUT-OFF &   FEEDER   The low water cut-off/feeder supplied with some   boiler serves as a low water cut-off (see above)   and also causes make-up water to be added to   the boiler should the water level drop below its   control point.   This type of control must be operationally tested   as for low water cut-offs and also to assure that   the make-up water is introduced as needed.   Carefully read the enclosed literature on the Low   2.4.4 LOW WATER CUT-OFF(S)   Most boilers are supplied with a float-operated   primary low water cut-off (and pump control or   Water Cut-off controls, particularly installing,   operating and servicing.   2.4.7 BOILER FEED SYSTEM   The boiler feed pump must be operationally   tested to assure that it can provide boiler   feedwater at the pressure and in the amount   needed for safe and reliable boiler operation.   2.4.6 OTHER CONTROLS   Additional controls as required for the particular   installation may also be provided. Refer to the   literature on these devices included in the Boiler   Manual. All such devices must be operationally   tested to assure reliable operation of the boiler   and system.   2.4.8 CHEMICAL FEED SYSTEM & SOFTENER   Check the performance of the boiler water   softener and chemical treatment system.   Chemically test the feedwater to be certain it   complies with the recommendations of the   chemical treatment consultant.   2.5 RECOMMENDED DRAFT AND COMBUSTION READINGS   ATMOSPHERIC GAS-FIRED BOILERS   BOILER SERIES   DRAFT AT BOILER CO2 @ HIGH   O2 @   HIGH FIRE   CO   (ppm)   SMOKE   NO.   OUTLET   (i.w.c.)   FIRE   F CL   K -0.01 TO -0.04   -0.02 TO -0.04   -0.02 TO -0.06   7.5 TO 8.5 % 5.0 TO 7.5 %   7.5 TO 9.0 % 4.8 TO 7.5 %   8.0 TO 9.5 % 4.0 TO 6.7 %   < 400   < 400   < 400   0 0 0 FORCED DRAFT GAS FIRED BOILERS   BOILER SERIES   DRAFT AT   BOILER   CO2 @   HIGH FIRE   O2 @   HIGH FIRE   CO   (ppm)   SMOKE   NO.   OUTLET (i.w.c.)   D HED   -0.01 TO -0.04   -0.01 TO -0.04   0.0 TO -0.04   7.5 TO 9.5 %   7.5 TO 9.5 %   4.0 TO 7.5 %   4.0 TO 7.5 %   < 400   < 400   < 400   < 400   < 400   < 400   0 0 0 0 0 0 CL   8.5 TO 10.0 % 3.2 TO 5.0 %   8.5 TO 10.0 % 3.2 TO 5.0 %   9.0 TO 10.0 % 3.2 TO 5.0 %   9.0 TO 10.0 % 3.2 TO 5.0 %   HECL   RV & RW   AB   0.0 TO -0.06   +0.50 TO -0.10   +0.25 TO -0.06   FORCED DRAFT OIL FIRED BOILERS   BOILER SERIES   DRAFT AT   BOILER   CO2 @   HIGH FIRE   O2 @   HIGH FIRE   CO   (ppm)   SMOKE   NO.   OUTLET (i.w.c.)   D CL   -0.01 TO -0.04   0.0 TO -0.04   10.0 TO 12.0 % 4.0 TO 7.2 %   10.0 TO 12.0 % 4.0 TO 7.2 %   11.5 TO 12.5 % 3.7 TO 5.0 %   11.5 TO 12.5 % 3.7 TO 5.0 %   < 400   < 400   < 400   < 400   0 0 0 0 RV & RW   AB   +0.50 TO -0.10   +0.25 TO -0.06   NOTE: THE VALUES FOR CO2 AND O2 ARE SHOWN FOR HIGH FIRE ONLY. THE VALUES FOR LOW   FIRE OR MID RANGE WILL GENERALLY BE LOWER, PARTICULARLY FOR ATMOSPHERIC GAS-   FIRED BOILERS. DRAFT SHOULD BE MEASURED APPROXIMATELY 24" FROM TOP OF BOILER,   BEFORE ANY DRAFT CONTROL.   2.5.1 DRAFT ADJUSTMENT - ATMOSPHERIC   GAS BOILERS   ARE MADE TO ASSURE ADEQUATE DRAFT   THROUGH THE VENTING SYSTEM.   2.5.2 DRAFT ADJUSTMENT -FORCED DRAFT   BOILERS   Draft adjustments are generally not necessary on   forced draft boilers. The draft must be measured   as part of the start-up procedure. The measured   draft at the boiler flue should fall within the   recommended range specified in the appropriate   table.   Refer to Section 1.8.6 for the adjustment method   for barometric dampers. Adjust the damper so as   to yield a draft which results in values of CO2 and   CO within the allowable limits listed above in the   appropriate table.   Draft adjustments are generally not required for   boilers equipped with draft diverters. The diverter   must   be   installed   without   modification.   Combustion readings are required, however, to   assure that the boiler operation is both safe and   efficient.   On some installations the draft may be excessive   due to a high chimney. In these cases, the draft   should be adjusted within the recommended   range specified in the above appropriate table.   This may be done using a barometric damper, a   restrictor, or a locking quadrant damper. Such   devices must be installed and adjusted by a   qualified technician.   Draft measurement should preferably be made   with an inclined tube manometer. If a draft gauge   is not available, check to be sure the flue gases   are being carried up the venting system by   passing a lighted taper or match around the edge   of the draft hood relief opening (or barometric). If   the venting system is operating correctly, the   match flame will be drawn toward the draft hood   relief opening. Otherwise the products of   combustion will tend to push the flame and   extinguish it.   2.5.3   COMBUSTION   ADJUSTMENTS   - FORCED DRAFT   Refer to the separate burner manual for the   procedures for burner adjustments. The burner   must be adjusted for smooth lightoff. Combustion   parameters should be within the range specified   in the above appropriate table. In no case should   the level of CO be allowed to exceed the limit   given, and the smoke spot reading must also not   exceed the value shown.   CAUTION   IF THE PRODUCTS OF COMBUSTION ARE   BEING EMITTED INTO THE ROOM (VENTING   SYSTEM NOT OPERATING CORRECTLY),   THE BOILER MUST NOT BE OPERATED   UNTIL PROPER ADJUSTMENTS OR REPAIRS   2.6 OPERATING INSTRUCTIONS   2.6.1 FAMILIARIZATION WITH MANUAL(S)   The user of the boiler must familiarize himself   with this manual and the burner manual for forced   draft boilers to be sure he is prepared to operate   and maintain the boiler properly.   The operating instructions should be kept in the   pocket in the boiler for F Series boilers, or   adjacent to the boiler for all others.   READ THE MANUAL BEFORE ATTEMPTING A   START UP.   2.7 MAINTENANCE SCHEDULE   2.7.1 POSTING SCHEDULE   Post a maintenance schedule in accordance with   the recommendations in this manual. A copy of a   typical schedule is included in this manual.   Section 3   CARE AND MAINTENANCE   STEAM BOILERS   CAUTION:   • • The boiler area should be kept free of combustible materials, gasoline and other flammable liquids.   The boiler and venting system must be kept free of obstructions of the air louvers and draft hood   relief openings.   • • The following procedures must be conducted as outlined to assure safe operation of the boiler.   All cover plates, enclosures, and guards must be in place at all times except during maintenance   and servicing.   3.1 REQUIRED PRECAUTIONS DURING TEMPORARY USE   GENERAL   1. Knowledge of burner/boiler operation.   A boiler is often utilized in new construction to   assist in curing of building components or to   provide temporary heat for the construction crew   or for other purposes during the time the building   is under construction. If precautions are not taken   during this time to protect the boiler, a great deal   of damage can occur before the ultimate owner   takes over the building.   2. Possession and understanding of boiler/burner   operating instruction manual.   3. Assurance that the boiler is fed with only   treated water at all times and that chemical   treatment and blowdown procedures are always   followed.   It is the mutual responsibility of the installing   contractor and the boiler owner to consider the   effect of temporary usage on the boiler warranty.   The following should be observed so as to assure   the longevity of the boiler.   4. Notification to the manufacturer (or   manufacturer's agent) to provide start-up services   if the boiler was purchased with start-up by a   factory representative.   5. Adherence to all of the start-up procedures   noted in the boiler/burner manual.   OPERATOR SKILLS/RESPONSIBILITIES   During the temporary use period, a single   individual must be assigned responsibility for the   care and operation of the boiler. This person's   responsibility must include, but not be limited to,   the following:   6. Considerations of warranty should the boiler be   used for temporary heat without adherence to the   recommended start-up and operating procedures   outlined in the instruction manuals.   3.2 CLEANING THE BOILER AND SYSTEM - NEW SYSTEMS   BOIL OUT PROCEDURE   In combination with system contamination,   The internal surfaces of a newly installed boiler   will have oil, grease or other protective coatings   used in manufacturing. Such coatings must be   removed since these coatings lower the heat   transfer rate and could lead to overheating of a   tube and reduce operating efficiency. Before   boiling out procedures may begin, the burner   must be ready for firing. The operator must be   familiar with the procedure outlined in the   boiler/burner operating instruction manuals.   bacteria may cause objectionable odors,   sometimes resembling natural gas. It is important   to keep these fumes from air intakes which would   distribute them throughout the building. On steam   humidification systems this is especially critical.   Consult your local water treatment chemist for   further information.   CAUTION   6. Fill the boiler with clean softened water until the   water level reaches the upper header. Then add   the cleaning solution into the upper header. Add   more clean water until the boiler is completely   filled. The water used for this initial fill should be   at room temperature, and must be softened as   noted.   The boil out procedure outlined must be   performed by, or under the direct supervision of,   a qualified technician. The chemicals used   present a hazard of burns and physical injury if   mishandled. Always use suitable face mask,   goggles, protective gloves and garments when   handling caustic chemicals. Do not permit the   chemical to come into contact with skin or   clothing. Always follow the safety precautions on   the container's label. Add chemicals slowly and in   small amounts to prevent excessive heat and   agitation. Do not add water to acid. Do not add   water to dry chemical. This will cause splattering   and/or explosion and severe risk of personal   injury.   7. After filling, fire the boiler intermittently (at low   fire) at a frequency as necessary to hold the   boiler solution at boiling point temperature. DO   NOT PRODUCE STEAM PRESSURE. Boil the   water, supervised at all times, for at least five   hours.   8. After the five hour boil out, begin to add a small   amount of fresh softened water so as to create a   slight overflow of the overflow pipe. This will carry   out impurities which have accumulated at the   water surface. Continue to apply heat and   overflow until the water emitted from the overflow   pipe clears. Then shut off burner.   Boiling out under pressure is not recommended.   If boil out under pressure is required, competent   assistance must be provided.   Your water consultant or water treatment   company will be able to recommend a cleaning or   boil out procedure. In the event that such service   is unavailable or as yet not selected, the following   may be used.   9. Let the boiler cool to 120 F or less. Then drain   the boiler. Use caution that the water is   discharged with safety.   10. Remove the inspection/cleanout openings in   the boiler upper and lower headers and wash the   waterside surfaces thoroughly using high   pressure water stream.   1. The boil out of the boiler and system is neither   difficult nor expensive. The chemicals needed for   cleaning are readily available. Trisodium   phosphate, and sodium hydroxide (lye) are the   most commonly used chemicals. Use only one   type of solution in the system. The amount of   chemical required will vary according to   conditions, but an amount of one pound of   chemical per fifty gallons of water is suggested.   11.   Inspect the boiler's internal (waterside)   surfaces thoroughly after the procedure. If the   surfaces are not clean, repeat the boil out.   12. After boil out, close all openings. Install relief   valves, gauge glasses and other components as   necessary. Completely fill the boiler with fresh,   softened, ambient temperature water. Fire the   boiler at low fire until water temperature of at least   180 F is reached. This will drive off dissolved   gases.   2. Before introducing the solution into the boiler,   an overflow pipe should be attached to the top of   the boiler and routed to a safe point of discharge.   3. Remove all safety valves to ensure that none   of the solution will come into contact with the   valve seats. Use care in removing and reinstalling   valves.   13. The boiler is now ready to operate.   4. All valves in the piping to and from the system   must be closed to prevent the chemical solution   from getting into the system.   IMPORTANT   If boiler is not to be operated within 24 hours, a   lay-up procedure is required. Refer to instruction   for lay-up.   5. Gauge glasses must be protected from contact   with the boil out chemicals.   3.3 SYSTEM CLEAN OUT   Many boilers have been ruined with system   contaminants such as pipe dope, cutting oil,   metal shavings or chips and other debris which   are left in the piping. If these contaminants are   not removed, they will end up in the boiler.   During this system clean out, the boiler make-up   water must be properly softened and treated. At   the conclusion of the system clean out, the   condensate must be reconnected.   For old or existing steam systems, the installation   process may have jarred debris loose. Following   the boil out of the new boiler, the condensate   should be wasted until it is within proper   guidelines. Check all steam trap strainers to   assure their cleanliness. Refer to the succeeding   section on replacement boiler installations.   SYSTEM CLEANING PROCEDURE   For steam systems, the boiler will need to be   connected to the header utilizing steam to purge   the piping and thus push the debris out of the   system. However, at this time all condensate   must be wasted until it runs clear and water   analysis of the condensate indicates that it is free   of contaminants. Steam trap strainers must be   periodically opened and cleaned of any debris   which accumulates.   3.4 REPLACEMENT BOILER INSTALLATIONS:   PROTECTION AGAINST CORROSION & SEDIMENT   BOILER MUST CONTROL FEED WATER   The water feed to the boiler must be controlled by   the boiler-mounted water level control. It is   unacceptable to use gravity return or to let the   water feed be controlled by a condensate/   receiver/ condensate pump system. The water   feed to the boiler must be controlled:   the entire system. A chemical treatment company   should be consulted for the proper means of this   chemical cleaning.   Replace any piping considered to be deteriorated   beyond safe or cleanable condition. Flush the   system clean, being certain to isolate the boiler.   by a feed pump control which is mounted on   the boiler. This control is to activate the feed   pump on a boiler feed system. It will be   necessary to supply such a system if not already   installed. - OR -   by an automatic water feeder mounted on the   boiler. This is used only on systems requiring   100% make-up, such as humidification, steam   process, etc.   DO NOT FLUSH THE SYSTEM THROUGH THE   BOILER   NOTE: For some old systems, there is a   reluctance to clean the piping because of the   possibility of leaks occurring in badly corroded   lines. Should the customer refuse cleaning, it is   necessary to install filtration equipment. Install   either a fibrous filter or a centrifugal filter in the   boiler return piping. This will collect and remove   sediment from the system. A booster pump may   have to be installed as well to overcome the   additional pressure drop introduced in the line by   the filter. When filling the system, provide   chemical treatment as outlined in Section 3.5.   NOTE   It is not recommended to provide the make-up for   a closed steam heating system to the boiler by   means of a water feeder. It is preferred that   system make-up be connected to the condensate   return tank of a boiler feed system.   A boiler feed system may be used in conjunction   with an existing condensate receiver system by   allowing the receiver system to pump condensate   into the boiler feed system tank.   CAUTION   Failure to properly clean the system or to install   mechanical sediment removal equipment can   result in tube blockage and severe corrosion plus   damage to pumps, controls, and air removal   device.   CLEAN OR REPLACE ALL SYSTEM PIPING   AND HEATING UNITS   Arrange for chemical and mechanical cleaning of   3.5 BOILER WATER TREATMENT   PURPOSE OF WATER TREATMENT   WATER SOFTENER   Water treatment is required for satisfactory   operation of the boiler. It must be devised to   prevent depositing of scale and to prevent   corrosion from acids, oxygen and other such   harmful elements that may be in the water supply.   A qualified water treatment chemist should be   consulted and the water systematically treated.   It is highly recommended that a zeolite water   softener be used for all make-up to the boiler. It is   intended that this be used in addition to the   chemical treatment of the boiler. Water softening   removes calcium and magnesium, the primary   causes of hard boiler scale.   CONTINUOUS MONITORING REQUIRED   Water treatment should be checked and   maintained whenever the boiler is operating. The   boiler operator should be sure that the boiler is   not operating for long periods without proper   water treatment. Water treatment may vary from   season to season or over a period of time.   Therefore, the water treatment procedure should   be checked not less than four times a year, and   possibly more frequently as the local water   conditions may indicate.   OBJECTIVES   The basic objectives of water treatment are:   1. Prevent the accumulation of scale and   deposits in the boiler.   2. Remove dissolved gases from the   water.   3. Protect the boiler against corrosion.   4. Maintain the highest possible boiler   fuel efficiency.   5. Decrease the amount of boiler down   time from cleaning.   3.6 EXTERNAL "FIRE-SIDE" CLEANING   PURPOSE   If the buildup of soot is appreciable, the flue gas   venting system must be thoroughly inspected   internally as well, and cleaned as necessary.   Carbon (soot) is an insulator and is corrosive.   The heating surface of a boiler must be kept free   from soot accumulation to keep the boiler   operating at its highest efficiency and to avoid   damage from corrosion.   IMPORTANT   If either soot or condensation is apparent, a boiler   service technician should be consulted. The   presence of soot indicates poor combustion and   possibly hazardous boiler operation. Failure to do   so may result in fire, explosion potential, or   asphyxiation. A combustion test and burner   adjustments should be undertaken at once.   SOOT REMOVAL   If the yearly inspection of the boiler tube surfaces   reveals a build-up of either soot or rust (usually   due to condensation), the tubes should be   thoroughly brushed. (Tube cleaning brushes are   available from Bryan Steam) To inspect and, if   necessary, clean the tube surfaces and flue   collector, first remove the tube access panels.   Examine the exterior of the tubes for evidence of   soot or rust. Using a flashlight, carefully look   between the tubes. There should be an   unobstructed opening between all tubes, and the   top surfaces of the tube must be free from soot   accumulation. Also inspect the interior of the flue   collector. Brush or vacuum the soot from all   surfaces. Be sure to cover atmospheric burners   with a protective cover during cleaning to prevent   soot from falling into them.   Rust on the tubes indicates that boiler-operating   temperatures are too low. The set point of the   boiler operating control must be no less than   130 F for natural gas or propane firing, and   170 F for oil fired boilers. Boilers equipped with   outdoor reset control must also follow these   limits.   3.7 SUGGESTED MAINTENANCE SCHEDULE   DAILY   MONTHLY   1. Make visual inspection of gauges, monitors, and   indicators and record readings in boiler log.   1. Make visual inspection of linkage and proper   operation of flue, vent, stack, or outlet dampers. Check   draft as specified in Section 2 of this manual.   2. Make visual check of instrument and equipment   settings against factory recommended specifications.   2. Check float low water cutoff as described above.   3. Check operation of float type low water cutoffs to   ensure control is functioning. The lower piping   connections of float type level controls should have a   suitable blowdown valve piped into a proper drain. This   valve should be opened periodically to allow any sludge   accumulated in the control to be flushed out. On closed   loop water heating systems this should not be often   required. Consult manufacturer's instructions.   3. For those units equipped with a power burner, check   low draft, fan, air pressure and damper position   interlocks as specified in burner manual.   4. Check high and low gas pressure interlocks. Refer to   manufacturers instructions for correct procedure.   5. Check high and low oil pressure interlocks. Refer to   manufacturers instructions for correct procedure.   WEEKLY   1. On units equipped with firing rate control, verify that it   is functioning correctly by adjusting control and   observing if input changes accordingly.   ANNUALLY   1. Perform leakage tests on pilot and main gas or main   oil fuel valves as specified in manufacturers instructions.   2. Make visual inspection of igniter and pilot flame. For   an atmospheric unit, confirm pilot flame is as shown in   this manual (Section 1.9) and that the main burners light   off correctly (smoothly) and that the flame is clean and   normal. For units with a power burner, check pilot flame   signal strength as specified in burner manual.   2. Check operating control, high limit, low fire start   control, and low water cutoff as specified in   manufacturers instructions.   3. For units equipped with power burners, check air   atomizing interlock, fuel valve interlock switch, purge   switch, burner position interlock, and fuel changeover   control, as specified in burner manual.   3. Check pilot and main fuel valves for correct operation.   Open limit switch - make audible and visual check -   check valve position indicators and check fuel meters, if   supplied.   4. The boiler should be checked at least yearly by the   local gas utility company. Particular attention should be   paid to the pilot burner safety devices. The pilot burner   should be checked to ensure that prompt ignition of all   burners occurs as the gas valve opens. Refer to Section   1.9.   4. Confirm boiler area is free of combustible materials   and that there is nothing obstructing air openings, draft   hood relief openings, etc.   5. Check combustion safety controls for flame failure   and flame signal strength as specified in manufacturer's   instructions located at the back of this manual for   atmospheric units or in the burner manual for units   equipped with a power burner.   5. The flue gas passages and the exterior surfaces of   the boiler tubes should be inspected at least annually.   Any accumulation of soot or debris should be thoroughly   cleaned out.   6. If the yearly inspection of the boiler tube surfaces   reveals a build-up of soot (carbon) or rust, the tubes   surfaces should be thoroughly brushed. Failure to do so   may result in fire or asphyxiation hazards.   6. Check all limit controls as specified in manufacturer's   manual.   7. Check float low water cutoff as described above.   7. The boiler pressure vessel and piping should be   checked annually.   8. Check combustion safety control for pilot turndown   and refractory hold-in as specified in manufacturer's   instructions.   3.8 FLOAT-ACTUATED WATER LEVEL CONTROLS   Inspect float type water level controls for proper   operation. Visually inspect sight glasses for   evidence of scale forming residues. Refer to   section 3.9 for gauge glass maintenance.   On humidification or process systems, the   blowdown schedule should be based on   recommendation from a water treatment and   maintenance program specifically designed for   the boiler.   On closed steam heating systems, the float low   water cutoff should be blown down by means of   At the annual inspection, all float type level   controls should be disassembled, cleaned and   inspected thoroughly. When re-installed these   controls must be given an operational test.   opening   a blowdown valve on the lower   connection of the cutoff once per day.   3.9 WATER GAUGE GLASSES   INSTALLATION   INSPECTION   Check with the maintenance supervisor and   engineering for the proper glass to be used.   Compare the box and the glass label or marking   to ascertain that the gauge glass ratings or   temperature and pressure are suitable for use on   the boiler. Use new gaskets when replacing   glass. The gaskets used should be the same type   as those originally supplied with the boiler. Make   certain that the gauge glass valves are properly   aligned.   To examine for scratches, shine a bright   concentrated light at about a 45 angle. Anything   that glistens brightly should be inspected closely.   Any scratch which glistens and will catch a   fingernail, or crescent-shaped or star-shaped   mark is cause for replacement. This is because   scratches, corrosion, chips and surface damage   weaken the glass. If inner surface appears cloudy   or roughened, and will not respond to cleaning   procedures, this is evidence of chemical attack. If   severe, this is cause for replacement.   All bolts and nuts must be free running and well   lubricated, preferably with   a graphite type   REPLACEMENT OF GLASS   lubricant. Washers under nuts and bolt heads are   desirable. DO NOT tighten while equipment is in   operation.   Any glass that has been removed from its   mounting in process boilers, regardless of the   reason for removal, should be discarded and   replaced with a new glass and gaskets. Used   glasses may contain hidden damage and   represent a safety hazard.   MAINTENANCE   Inspect the gauge glass regularly for any signs of   clouding or scratching. In new processes, the   gauge glass should be inspected daily until the   need for replacement becomes apparent. This   will help establish the routine inspection cycle.   Be sure that the replacement glass is suitable for   service conditions.   Protective shields to keep cold air, water, or   falling objects from glass must be replaced.   The gauge glass should be blown down daily so   as to remove accumulated sediment from the   valves.   4.0 IDLE BOILER CARE AND LAY-UP   GENERAL   (when used) should be kept to a minimum so the   reduction of solids is achieved by the increased   manual blowdown.   Corrosion damage to boilers is often the result of   improper lay-up during non-operating periods.   Substantial damage can occur in only a few days   in proper precautions are not taken. This damage   is irreversible and will reduce boiler reliability,   increase maintenance costs and eventually   shorten the useful life of the boiler tubes.   WASHDOWN   As the boiler cannot be washed immediately, the   heat in the boiler may cause baking of residual   sludge. The boiler should not be drained until   cooled enough to prevent this. However, never   leave the boiler filled with water for any extended   period of time without taking measures to prevent   corrosion.   Idle boilers are vulnerable to attack when air   contacts untreated wet metal surfaces. To prevent   corrosion, the boiler metal must be protected by   either keeping the surfaces completely dry or   excluding air from the boiler. Air exclusion is   accomplished either by keeping the boiler   completely full of water (short term lay-up) or filling   the boiler with nitrogen gas (long-term lay-up).   The nitrogen gas prevents air infiltration and does   not react with the metal.   LAY-UP CONSIDERATIONS   There are two basic methods of steam boiler lay-   up: Wet lay up or Dry lay-up. The choice of which   method should be used depends on:   The possibility that the boiler may need to be   placed in operation on short notice.   Disposal of lay-up solutions   In addition to the corrosion damage that occurs,   the metal particles that are released will form an   insulating scale on the tubes when the boiler is   returned to service. These corrosion products will   accumulate on critical heat transfer areas of the   boiler, increasing the potential for localized   corrosion and over heating.   Freezing potential   Wet Lay-up is recommended for relatively short   outages, such as seasonal lay-up. This method   has the advantage of allowing the boiler to be   brought on line with short notice. But it can pose   problems if there is any likelihood of freezing.   PRE-OPERATIONAL CLEANING AND LAY-UP   Proper lay-up techniques must be used on an idle   boiler even if it has never been in operation.   Before pre-operational lay-up, the boiler must be   chemically cleaned as outlined in Section 3.2 of   this manual. This is required, as noted in this   section, to remove preservatives, oil and grease   from the tube surfaces. Follow the short term or   long term lay-up procedure as appropriate.   Dry Lay-up is recommended for longer periods of   boiler shut-down or storage. But it is practical only   if boiler can be drained hot (120 F to 170 F) or if   external drying can be provided.   WET LAY-UP OF STEAM BOILERS - SHORT   TERM   In the wet lay-up procedure, the boiler is to be   filled with chemically treated water and sealed to   prevent air in-leakage. Nitrogen gas under slight   pressure can also be used to displace air and   protect the boiler surfaces from corrosion. The   following steps should be taken for wet lay-up of a   boiler:   TAKING BOILERS OFF LINE   In operation, boiler water contains suspended   solids which are held in suspension due to water   circulation and the action of treatment chemicals.   Unless care is exercised when draining the boiler,   these suspended solids settle on the tube   surfaces and will air dry to an adherent deposit,   sometimes requiring chemical cleaning to remove.   In addition, these deposits may be misleading   regarding the effectiveness of the chemical   treatment program.   1a. Procedure for operational boiler:   At least thirty minutes before the boiler comes off   line, add the following chemicals:   Sodium Sulfite - 0.5 lbs. per 100 gallons water   Polymeric Sludge Dispersant - 0.1 lbs. per 100   gallons water   Caustic Soda - 0.3 lbs. per 100 gallons water   PRE-SHUTDOWN PRECAUTIONS   For a period of three to seven days prior to   shutdown, manual blowdown frequency should be   increased. During this period, the lower   conductivity limit should be below 3500 micro-   mohs per centimeter. The feed of internal   treatment must be increased to maintain a specific   residual concentration. Continuous blowdown   1b. Procedure for idle boiler:   If the boiler has never been on line or has been   out of service for cleaning - Select the highest   quality water available to fill the boiler. Steam   condensate, softened water, filtered fresh water,   and boiler feedwater are generally acceptable for   lay-up. Raw city water is not recommended and   should not be used.   chemical. Then repeat Step. 2. Pay attention to   the maintenance of the valves being used to   isolate the boiler to prevent leakage and resultant   dilution of the lay-up solution.   Prepare the chemical solution described in (1a) in   a separate tank. Adhere to the safety precautions   described in Section 3.2 of this manual. Add the   concentrated lay-up solution to the boiler during   the time it is being filled.   ALTERNATE METHOD   An alternate wet lay-up method is to pipe clean   continuous blowdown water from a properly   treated boiler into any convenient bottom   connection on the idle boiler, allowing the water to   flow through the boiler and out the top (through   any convenient top opening) to the sewer. This   method will insure a continuous, complete fill with   warm, properly treated water. It also prevents in-   leakage of air by keeping the boiler slightly   pressurized. It may also provide enough heat to   keep the fireside of the boiler dry and possibly   produce adequate freeze protection.   After the boiler is filled and the lay-up solution has   been added, the boiler is to be operated for thirty   minutes at low fire to circulate and mix the   chemicals.   2. After filling, the boiler must be closed or   blanked tightly. The power supply to the boiler   must be cut off. Vent all air from the top of the   boiler to allow complete fill with the required   solution. Nitrogen gas at 5 psig may be introduced   though a suitable opening to prevent air in-   leakage during the lay-up period. An alternative to   the nitrogen gas (see safety precautions under dry   lay-up) is to install a 55 gallon drum or auxiliary   vessel as shown in Figure 3.11A. This is to be   fitted with a cover and filled with properly treated   water. This vessel or drum should be connected   to an available opening in the top of the vessel. Its   purpose is to create a hydrostatic head and to   allow a ready visual check of water level loss or   in-leakage during the lay-up period.   DRY LAY-UP OF STEAM BOILERS - LONG   TERM   The dry lay-up method recommended requires   that the boiler be drained, dried as completely as   is possible, all opening and valves closed.   Nitrogen gas at 5 psig is introduced to the boiler to   pressurize it and prevent air in-leakage. The   success of the procedure depends on the   thorough drying of the boiler metal surfaces after   draining and the exclusion of air during the lay-up.   CAUTION   The use of nitrogen for blanketing is   recommended in both the wet and dry lay-up   procedures. Even though nitrogen in dilute   quantities is non-toxic, it will not support life.   Precautions must be taken before entering   equipment filled with nitrogen for inspections or   any other purposes. These precautions shall be   as follows:   disconnection of nitrogen supply line   complete purging and venting of the equipment   with fresh air   testing oxygen levels inside before any attempt   to enter   Figure 3.11A: WET LAY-UP STATIC HEAD   DRUM   all confined entry guidelines applicable to site   must be followed   3. During lay-up, test the boiler weekly to assure   the proper levels of sulfite and alkalinity. To do   this, take a sample of the boiler water from the   surface blowdown line or other high point. The   test results should be:   Sodium Sulfite 200 ppm minimum   Phenolphthalein Alkalinity (as CaCO3)   400 ppm minimum   Appropriate caution signs shall be posted around   the equipment to alert personal that nitrogen   blanketing is in use. A boiler laid up dry must be   tagged with information that the unit is not to be   operated until the boiler is properly refilled.   If the tests indicate chemical concentration has   decreased, chemical may be introduced to the   boiler by putting it in the drum shown in Fig.   3.11A. Then lower the boiler water level to   introduced it into the boiler. Then operate the   boiler at low fire to circulate the water and mix the   1. Drain the boiler before the steam pressure falls   to zero. Then pressurize with 5 psig nitrogen gas   through a suitable top opening during draining.   The nitrogen pressure is to be maintained through   draining and subsequent storage.   An alternate method is to completely dry a clean   boil (by blowing hot dry air though the boiler) and   then purge the air from the boiler and pressurize   with 5 psig nitrogen. Be aware that all metal   surfaces which are not completely dry are   vulnerable to corrosion, particularly if oxygen is   present.   1. If the boiler was pressurized with nitrogen,   disconnect the nitrogen supply source and vent   the boiler.   2. Using the blowdown valve, drain the boiler   partially and make up with feedwater so as to   dilute the chemical residuals to operating   concentration levels.   2. If a boiler has been down for repairs and is to   be laid up, it should be operated to pressurize with   steam and then drained and pressurized with   nitrogen as in step 1.   3. After the boiler water concentrations and the   water level are returned to proper operating   conditions, the boiler can be started in the normal   manner.   3. All connections must be blanked or tightly   closed.   After Dry Lay-Up   To start an idle boiler after dry lay-up, use the   following procedure:   Note: Operating boilers must be removed from   service to minimize adherence of boiler water   suspended solids on boiler metal surfaces. Refer   to previous instructions for boiler washdown.   1. Disconnect the nitrogen supply source and vent   the boiler in a safe manner - external to the   building and away from air intakes. Then   thoroughly purge the boiler of nitrogen with dry air.   RETURNING IDLE BOILER TO SERVICE   After wet lay-up   To start an idle boiler after wet lay-up, use the   following procedure:   2. The boiler was to have been cleaned before the   lay up procedure. So it is necessary only to fill the   boiler with properly treated water. Then proceed   with start-up.   |